Spread Budgets Using Pre-defined Spread Methods
You can spread budgets using spread methods that have been previously defined in Cobra.
To spread budgets using pre-defined spread methods, complete the following steps:
- Display the Project view of the project you are updating and select the resource to be spread.
- In the Assignments group on the Project Edit tab, click .
- On the Spread dialog box, select the spread curve method that you want to use.
-
Click
Select.
Cobra spreads the budget using the spread curve method that you selected and displays the updated information in the Time-phase pane.